Who issues permits
The City of Bainbridge Island's Planning and Community Development (PCD) Department "coordinates and manages development and land-use activity on Bainbridge Island." Its Building Division is "responsible for ensuring that construction and development within the City of Bainbridge Island comply with the minimum Building Code requirements adopted by Washington State". Source [3]Source [2]
How to file
- "All building and land use permit applications will only be accepted as electronic submissions via the Public Permit Portal." Source [1]
- "Permit applications must be submitted electronically via the portal; alternative submittal methods are not accepted. A portal account is required to submit applications, pay fees, schedule inspections, and manage active permits." Source [1]
- The City's Clariti Permit Guide "provides helpful prompts for permitting based on project type and GIS mapping tools", and you can use it as a guest. Source [1]
- "Complete building permit applications include the minimum basic project information and the required submittal documents, such as plan sets and drawings." Source [2]
- For a fee estimate on a potential project, the Permitting page says to email permittingsubmittal@bainbridgewa.gov. Source [1]
Review times
- "The timeline for the first cycle of review of permit applications is typically 30 days for building projects and 60 days for planning projects. The review timeline starts from the date a submitted application is deemed complete. Additional review time will be required for resubmitted information and/or project revisions." Source [1]
- "Building permits expire 180 days after permit issuance, or 180 days after the last approved inspection activity is performed." Source [1]
Worth knowing
- "The required permits must be approved and issued before beginning project activities." Source [2]
- "Projects within a critical area or shoreline designation typically require additional land use permits from the Planning Division." Source [2]
- The City's handout says "All development within 200’ of ordinary high water requires the submittal of a Shoreline Substantial Development Exemption prior to the submission of a building permit." Source [4]
- "Owners may act as the builder and construct all portions of a building. However, if any or all of the construction (including plumbing and mechanical) is hired out, contractor information must be provided." Source [2]
- "The Department of Labor and Industries is responsible for electrical permits." Source [2]
- "The 2021 Building Code and the 2021 Fire Code are effective as of March 27, 2024." Source [2]
- On August 31, 2026 the City announced that its Council adopted Ordinance 2026-10 on August 25, an interim development regulation ordinance that "Adopts a new zoning map and new zoning codes for six months or until the final Comprehensive Plan and Winslow Subarea Plan and their new zoning codes are adopted." Check current zoning with PCD before you design. Source [5]
Topic guides
Bainbridge Island: what the office says about common projects
Each guide quotes the rule from the office's own page and names the page and the date we read it.
ADU (accessory dwelling unit)
Permit required
The City of Bainbridge Island's pre-approved ADU flyer says "The owner or applicant must apply for an ADU building permit with the City of Bainbridge Island Planning & Community Development (PCD)." The plans are free to use, but the City…
Home addition
Permit required
The City of Bainbridge Island's "When Do I Need a Building Permit?" handout says a building permit is required before any construction work involving framing, sheetrock, insulation or new construction work.
Deck
Depends on the project
The City of Bainbridge Island's "Work Exempt from Permitting" bulletin exempts a deck that does not exceed 200 sq ft in area, is not more than 30 inches above grade at any point, is not attached to a dwelling, and does not serve an exit…
Basement finishing
Permit required
Basement finishing that involves framing, sheetrock or insulation needs a building permit on Bainbridge Island, because the City's handout requires one "before any construction work or activity involving framing, sheetrock, insulation or…
Garage or shop
Depends on the project
The City of Bainbridge Island exempts a one-story detached accessory structure used as a tool or storage shed, playhouse or similar use only when the floor area does not exceed 200 square feet.
Fence
Depends on the project
The City of Bainbridge Island lists "Fences not over 7 feet high" as work that does not need a building permit.
Sources
Where this comes from
Compiled from Bainbridge Island's published rules; oldest source checked
JKM pulls the permit as part of the job