Short answer

Permit required

The City of Bainbridge Island's "When Do I Need a Building Permit?" handout says a building permit is required before any construction work involving framing, sheetrock, insulation or new construction work. The handout does not use the word "addition", but an addition is framed, insulated new construction, which is what that sentence names. The Building Division adds that "Permits are required for most construction activities on Bainbridge Island." Source [1]Source [2]

The rule, quoted

From the "When Do I Need a Building Permit?" handout:

A building permit is required before any construction work or activity involving framing, sheetrock, insulation or other types of remodel or new construction work.

From City of Bainbridge Island: When Do I Need a Building Permit? (handout), read October 13, 2026

From the Building Division page:

Permits are required for most construction activities on Bainbridge Island.

From City of Bainbridge Island: Building Division, read October 13, 2026

What to submit

The Permitting page says a complete application "will include" the following. Source [3]

  • Assessor's Tax Parcel Number Source [3]
  • Owner information: name, address, phone number and email address Source [3]
  • Project site address Source [3]
  • Contractor information, including the contractor license number Source [3]
  • Submittals: "Supporting documents, including Site Plan, Plan Sets, and other required information." Source [3]

Worth knowing

  • "The required permits must be approved and issued before beginning project activities." Source [2]
  • The handout says "All development within 200’ of ordinary high water requires the submittal of a Shoreline Substantial Development Exemption prior to the submission of a building permit." Source [1]
  • "The timeline for the initial review of building permit applications is generally 30 days from the date a submitted application is deemed 'complete'." Source [2]
  • The Building Division says "The Department of Labor and Industries is responsible for electrical permits." Source [2]

Sources

Where this comes from

  1. City of Bainbridge Island: Building Divisionbainbridgewa.gov · read
  2. City of Bainbridge Island: Permittingbainbridgewa.gov · read

Compiled from Bainbridge Island's published rules; last checked

JKM pulls the permit as part of the job

Call Ian Laughlin at (206) 226-1988, or send the address and the scope. We find the right office and take it from there.